RAPID CITY METROPOLITAN PLANNING ORGANIZATION Agenda Item Summary |
|||||
|
|||||
Meeting Date: 12/11/2014 |
City Council: 12/15/14 |
||||
Staff Contact: Kip Harrington, Planner III |
Planning Commission: N/A |
||||
Petitioner: N/A |
PW Committee: 12/9/2014 |
||||
Location: N/A |
Metropolitan Planning Organization: 12/11/2014 |
||||
Agenda Title: |
|||||
14TP045- Amendment #15-002 to the 2015-2018 Transportation Improvement Program |
|||||
Summary: |
|||||
Amendment #15-002 to the 2015-2018 Transportation Improvement Program defers an Interstate Maintenance Project from 2016 to 2017, defers a State Highway System Urban Project in Rapid City from 2015 to 2018, defers three State Highway Urban System Projects from 2016 and 208 to the Developmental STIP, and defers a Local Urban Systems Project from 2015 to 2018. Due to the heavy work load in Rapid City area specifically and the region on a whole, the cost of projects is higher than estimated due to the shortage of available contractors. It has become prudent to defer the identified projects to balance the work load and encourage more competitive bids. |
|||||
Funding Source & Fiscal Impact (if applicable): |
|||||
Project Category / Description |
Project Year |
Original Cost |
Revised Cost |
Net Change |
|
Interstate Maintenance Project |
|
|
|
|
|
IM 0901(38)40 5580 I90E, I90W Meade I90 - EBL & WBL between Exits 40 (Tilford) and 44 (Piedmont) & Reconstruct Exit 44 (Piedmont) Interchange-Reconstruct with PCCP Surfacing and Structure & Exit 44 Interchange |
2016 to 2017 |
$30.492
$0.000 |
$0.000
$31.102 |
-$30.492
+$31.102 |
|
State Highway Urban System Projects |
|
|
|
|
|
P 0044(190)45 0515 SD44 Pennington Intersection of SD11 (Omaha St.) and East Boulevard in Rapid City-Intersection Improvements |
2015 to 2018 |
$0.883
$0.000 |
$0.000
$0.937 |
-$0.883
+$0.937 |
|
P 0231(12)80 02R5 SD231, SD231N, SD231S Pennington SD231, SD231 N&S - Fm Sheffer St. to Sturgis Road in Rapid City- Urban Grading, Roadway Lighting, Storm Sewer, Curb & Gutter, Sidewalk, Traffic Signals, Pedestrian Crossing & PCC Surfacing |
2016 to Devel. STIP |
$10.820 |
$0.000 |
-$10.820 |
|
P 044(167)44 027K SD44, SD44E, SD44W Pennington SD44 ( Omaha St.) - Fm Mt. View Rd to the start of the divided lanes near 12th Street- Urban Grading, Storm Sewer, Curb & Gutter, Sidewalk, Traffic Signals, PCC Surfacing, Lighting |
2018 to Devel. STIP |
$6.330 |
$0.000 |
-$6.330 |
|
P 0231(13)79 03CP SD231, SD231N, SD231S Pennington SD231 (W Chicago/W Omaha) - Fm Sheffer St to Mt. View Rd (SD44) in Rapid City- Urban Grading, Storm Sewer, Curb & Gutter, Sidewalk, Traffic Signals, PCC Surfacing, Str. Repair & Widening over Rapid Creek, Lighting |
2018 to Devel. STIP |
$6.418 |
$0.000 |
-$6.418 |
|
Local Urban Systems Project |
|
|
|
|
||
P1774(06) 02SF Pennington East Boulevard and East North St. fm St. Joseph St. N and E to Herman St. in Rapid City-PE, Grading, Intersection Improvement, Traffic Signals, Curb & Gutter, Storm Sewer, Sidewalk, PCCP, Lighting |
2015 to 2018 |
$5.346
$0.000 |
$0.000
$5.673 |
-$5.346
+$5.673 |
||
|
|
|
|
|
||
Recommendation: |
||||||
Action: Approve the 2015-2018 Transportation Improvement Program Amendment #15-002 |
||||||
Options: |
||||||
|
||||||
Attachments & Links |
||||||
|
||||||
|
|
|
||||